Total Cost Control in Project Management via Satisficing

成果类型:
Article
署名作者:
Goh, Joel; Hall, Nicholas G.
署名单位:
National University of Singapore; University System of Ohio; Ohio State University
刊物名称:
MANAGEMENT SCIENCE
ISSN/ISSBN:
0025-1909
DOI:
10.1287/mnsc.1120.1653
发表日期:
2013
页码:
1354-1372
关键词:
project management time and cost control under uncertainty robust optimization and satisficing linear decision rule
摘要:
We consider projects with uncertain activity times and the possibility of expediting, or crashing, them. Activity times come from a partially specified distribution within a family of distributions. This family is described by one or more of the following details about the uncertainties: support, mean, and covariance. We allow correlation between past and future activity time performance across activities. Our objective considers total completion time penalty plus crashing and overhead costs. We develop a robust optimization model that uses a conditional value-at-risk satisficing measure. We develop linear and piecewise-linear decision rules for activity start time and crashing decisions. These rules are designed to perform robustly against all possible scenarios of activity time uncertainty, when implemented in either static or rolling horizon mode. We compare our procedures against the previously available Program Evaluation and Review Technique and Monte Carlo simulation procedures. Our computational studies show that, relative to previous approaches, our crashing policies provide both a higher level of performance, i.e., higher success rates and lower budget overruns, and substantial robustness to activity time distributions. The relative advantages and information requirements of the static and rolling horizon implementations are discussed.